Tokat New Airport Runway Project / Tokat

The contract of the project which we undertook within the framework of the Runway Construction for Tokat New Airport was signed on 12.07.2018 and started on 18.07.2018.
The project scope includes 45 meters wide and 2700 meters long concrete track, 1265 meters long taxi way, 29.000 m2 apron, 53.200 m2 ring road, 10.400 meters firewall, 19 sentry clubs, vor and regulator buildings.
Work load of the project increased nearly 15% in July of 2019 and estimated cost was revised.